“While this lawsuit focuses on the project’s competitive bidding and ownership process, our concerns about the proposed transmission line’s impacts on Anza-Borrego Desert State Park and surrounding communities remain.This legal action is one part of our broader effort to protect the Park. We continue working alongside our partners, community members, and public officials through advocacy, public education, and regulatory engagement,” the Foundation states on Facebook, adding, “We’re committed to keeping you informed and doing everything reasonably within our power to protect Anza-Borrego for future generations.”
Miriam Raftery • November 26, 2026
SDG&E Changes Proposed Route of Golden Pacific Powerlink; Anza-Borrego Foundation files antitrust lawsuit
Share

By Miriam Raftery, www.eastcountymagazine.org
The Anza Borrego Desert Foundation and a coalition of others filed a lawsuit late last week against SDG&E and the California Independent Systems Operator (CAISO alleging CAISO violated antitrust law by awarding the Golden Pacific Powerlink project to SDG&E, despite another company putting in a much lower bid. But SDG&E has doubled down on its determination to run the line through California’s largest state park.
On Nov 20, SDG&E released a revised proposed route for the controversial 150-mile high voltage powerline that would bypass Temecula, but slice through Palomar Mountain and other northeast county communities including tribal lands, while still traversing the heart of Anza Borrego Desert State Park despite strong opposition from Borrego residents and environmental groups.
The new preferred route
The new route would slice through Fallbrook, Pauma Valley and along State Route 76, through Valley Center and the most populated area of Palomar Mountain along the southern portion of the mountain. It would also threaten waterways in Warner Springs, Lake Henshaw, and five bands of the San Luis Indian Water Authority, as well as march through scenic areas and habitat for endangered Peninsular Bighorn Sheep in Anza-Borrego Desert State Park.
The antitrust lawsuit
“The lawsuit challenges how SDG&E gained responsibility for the proposed Golden Pacific Powerlink transmission line after another company (Horizon West Transmission LLC) was selected through a competitive bidding process,” the ABDF announced on Facebook. “It alleges violations of California’s antitrust and unfair competition laws.” The suit also contends that SDG&E customers would shoulder higher utility rates to fund the line, in a region already paying among the highest utility costs in the U.S.
The suit was filed by attorneys from Aguirre & Severson LLP in San Diego and DeBlase Brown Eyerly LLP of Los Angeles on behalf of two nonprofits, ABDF and Borrego Community Development Corporation, as well as 21 individuals.
The suit states that Horizon West’s base capital cost was around $1 billion for both the 500 kV transmission line from Imperial County to Orange County as well as a new substation, compared to SDG&E’s estimated capital cost of $1.62 billion to build only the transmission line, not the substation. The suit accuses utilities of conspiring with CAISO to allow SDG&E to fund, build and maintain the powerline while Horizon West would be responsible for the substation.
Bill Powers, a plaintiff in the suit, told inewssource he believes the need for the project should be reassessed and solar panels analyzed as a more affordable and less environmentally destructive solution to meet electricity demands. “It’s just become an existential nationwide fight to kneecap rooftop solar and double down on the need for transmission,” he said.
New proposed route draws opposition from communities across northeast San Diego County
SDG&E, after hearing community input from more than 1,500 people at four in-person and four-online forums, has announced it has revised its proposed route to eliminate going through Temecula, where it had drawn strong opposition from Temecula’s mayor, city council, and local tribes. The utility now plans to ask the California Public Utilities Commission (CPUC) to approve the alternative South Mountain Route because it has “potential to reduce certain environmental impacts and address engineering challenges.
Like every potential route, however, it presents different considerations that require continued study and engagement with potentially affected communities,” SDG&E stated in its announcement of the changes. The utility pledged to engage with potentially affected communities to hear concerns and provide information.
SDG&E has posted updated maps and additional information on the Golden Pacific Powerlink project website.
Community groups along the proposed powerline route organize opposition
Below are comments posted on social media from key stakeholder groups.
City of Temecula: The City of Temecula issued a statement praising the collective efforts of the city and community to get Temecula removed as the preferred route, it also notes that Temecula remains a potential option as `The Riverside County Alternative’ route. The statement affirms that “the City’s opposition remains unwavering—and our work will not be done until Temecula Valley is removed from considering entirely.”
Anza-Borrego Foundation: The nonprofit seeks donations to fund its lawsuit against SDG&E and CAISO.
For more information you can https://theabf.org/park-threat/, read about Anza-Borrego Desert State Park, and donate to the Anza-Borrego Foundation to fund its efforts to protect the park, including the lawsuit.
Save Palomar Mountain: “Abandoning the Riverside County Route weeks before filing concedes that Temecula’s multi-agency record was untenable. Yet the South Mountain Route trades one unmitigable set of impacts for an equally formidable wall of water districts, tribal sovereigns, and backcountry fire coalitions—strengthening the case for an SB 1006 non-wires alternative.”
The group cites obstacles along the South Mountain Route including “direct collision with sovereign water immunity” from three districts as well as causing “evacuation choke points” that would make it difficult for community and tribal members to evacuation in a wildfire. The line would skirt he Pala, Pauma and Rincon reservations as well as five bands of the San Luis Indian Water Authority, triggering strict AB 52 Tribal Cultural Resource protections as well as threatening evacuation routes along State Route 76 and East Grade Road.
Learn more SavePalomarMountain.org.
Save Pauma Valley: The citizens’ group notes that Cal Fire found SDG&E lines responsible for starting the 2007 Witch, Guejito and Rice fires in North County and voices fears that 200-foot-tall towers in fire-prone areas could delay firefighters from extinguishing fires that start under an energized line, noting it can take time to shut off high voltage lines. “The CPUC has said no before,” Save Pauma Valley notes. “In 2002 it rejected SDG&E’s Valley-Rainbow 500 kV line as not needed and not cost-effective.”
The group urges the public to visit https://savepaumavalley.org and to join the coalition opposing the line at https://wesavecalifornia.org.
Fallbrook Land Conservancy: The group opposes the Golden Pacific Powerlink as proposed, citing responsibility to protect natural habitats, wildlife corridors, watersheds, and open spaces. The Conservancy’s concerns fall into three categories: “(1) the larger question of whether this transmission is necessary at all, (2) the local question of how to minimize environmental damage if it is ultimately constructed, and (3) the fairness of the imbalance between regional benefits and local environmental consequences.” Learn more at https://www.fallbrookland.org/nwes/goldpacificpowerlin under News.